§ 17.20.160. Checking—Fees.  


Latest version.
  • A.

    The subdivider shall pay to the county fees for the surveyor's services in checking the final map based on the current fee schedule as established from time to time by resolution of the board of supervisors. All fees shall be paid prior to the time the map is set for approval by the commission. Said fee includes the cost of printing copies of the final map. After recording, one set of intermediates will be sent to the surveyor who prepared the map.

    B.

    Prior to the execution of the certificates on the original tracing, the subdivider shall submit two sets of prints of the map and certificate sheet to the county surveyor. The preliminary prints shall be accompanied by a preliminary title report of the property shown on the map and by traverse sheets prepared by the subdivider's engineer or surveyor showing by mathematical closures proof of the accuracy of all surveying information shown on the map. These shall be submitted on computer output sheets in a readily usable printed form. If computation sheets are not in an acceptable form, they shall be rejected and returned with the maps.

    C.

    The error of closure for a traverse of the boundaries of the tract blocks or lots shall be one in five thousand or less.

    D.

    Within twenty calendar days after submission of the required documents, the county surveyor shall approve the same or disapprove them and return to the subdivider for correction.

(Ord. 80-446-F § 1, 1980; Ord. 80-446-E § 2, 1980; Ord. 74-446 Art. II § 30, 1974.)